Remedial works following inspection

Remedial works

If it is necessary to schedule remedial works as a result of an inspection you can do this directly from the maintenance tab on the inspection form itself. Follow the standard process for adding a new maintenance task (see section on adding maintenance tasks for details).

All scheduled tasks and actual works enquiries and orders that relate to this inspection will automatically be visible in the maintenance (1) and works (2) lists on the inspections record

IMPORTANT NOTE: By adding the remedial maintenance tasks directly from the inspection record, the remedial works are linked not only to the resource they relate to but also to the inspection itself, thus providing a full history of events and actions.

Previous Lesson: Stock and condition checks Table of Contents Next Lesson: Adding Valuations